Stage 1
Examine sub floor and measure area needing to be done. The customer also decided to have a Mat fitted at entrance of hall, so measure the size needed
Stage 2
Fit floor grade ply to the areas to be free tiled and insuring to fix it every 4 inches. in this example kitchen,utility,hall and toilet
Stage 3
Now floor is prepared, the Camaro tile can be marked out square to the kitchen and other areas. Once happy the tiles are in the right place pencil a mark where they need to go.
Stage 4
Put pressure sensitive glue to half the area being fitted to make sure you don’t over glue so the glue doesn’t go off.
Stage 5
Once glue is ready to lay. Put first line of tiles down with grout inlet where marked. Once first line is on floor you can work out brick design tiles with grout inlet. Once all layed clean any excess glue off floor.